4.5 Million Tons PTA Installation Project Mobile Pipeline Prefabrication line


Return to List

Product Description

Site size: Mobile pipeline prefabrication line, 120m* 17m

Design capacity: 2000D./ day

Construction period: 120 days

Case introduction:

1. Specifically for pipeline prefabrication projects with "short construction period and large workload", Aote integrated the design of "mobile pipeline prefabrication production line and workstation". This novel model is to integrate the "pipe cutting/groove", "group pair" and "automatic welding" respectively in the container that is convenient for changing fields and transferring, which can be easily transferred with the project and quickly form a more comprehensive production capacity.

2, can achieve the whole ground logistics conveying system, effectively improve the production line logistics efficiency.

3. Manpower requirements: 18 operators, 4 riveters, 4 welders, 23 lifting and auxiliary workers.

 